Carolyn Tice owns a house at the end of Jefferson Avenue, where the land dips sharply into Green Acres preserved open space adjacent to a loop of the Rancocas Creek. A damaged stormwater outfall at this location has washed out so much soil that a 30-foot-deep ravine has formed and is threatening to swallow parts of Tice’s front yard. Every professional who has looked at the problem acknowledges it as serious, but Ms. Tice says the township is not communicating adeqautely with her about what is being done to fix the problem.
Tice attended the November 9th, 2026 council meeting to once again ask about progress on the stormwater outfall reconstruction project. She addressed Mayor Banks, describing her previous inquiries which stretch back into 2023. She said it seems the project to fix the storm drain and its damage have not made progress. She noted that the Mayor had personally visited the site and promised the project would be completed last July.
“You told me the project would be finished in July. What year did you mean?” Carolyn Tice
Ms. Tice speculated that the township is tired of hearing from her but she would not stop inquiring until she gets clarity on the project.
“I walked along that edge and my foot goes down. it’s scary. I’m losing my property and you raise my taxes. What am I paying for? Carolyn Tice
Mayor Banks addressed Ms. Tice’s complaint by acknowledging that things take too long in government, but said the project is “moving along” and he will check with the Township Manager Josh Brown [who was absent] regarding whether “the bids came back”.
WHAT HAPPENED?
A stormwater outfall at the end of Jefferson Avenue discharges into the wetlands just beyond. The Reporter’s review of historic aerial photos and topographic maps for the area reveal that significant erosion appeared in 2023. More recent aerial photos show an erosion ravine that toppled a nearby mature tree [See image]. The Reporter’s visit to the site confirms that the ravine is about 30 feet deep, with steep and unstable sides.
WHAT IS DELAYING THE STORM OUTFALL REPAIR?
Mount Holly attempted to get aid from the NJ Department of Transportation Local Aid Infrastructure Fund. By 2024, the town was awarded a Local Aid grant of $625,000 for construction of a retaining wall and stormwater facilities.
The Reporter discovered that in June 2026, the town submitted an application for a waterfront development permit to the NJDEP because our engineer designed a massive, terraced outfall facility to be constructed in Green Acres protected wetlands of the Rancocas Creek. The construction required a permit from the NJDEP which was issued on October 8, 2026. The permit noted that the construction would “result in the disposal/diversion of Green Acres encumbered parkland” and that the town must therefore coordinate its work with Green Acres.
A November 16, 2026 email from Township Manager Josh Brown stated that our engineer reached out to Green Acres. A Green Acres representative told The Reporter that engineer had only just placed his call on the same day as Brown’s email.
The apparently lackadaisical tempo in actions required by the construction grant and permit raised questions that The Reporter put to the Township Manager. When was Alaimo prompted to begin engineering plans for work on the stormwater outfall reconstruction and when were bids sought for contractors to begin that work?
The Township Manager has not responded to this email which would seem to match the behavior described by Mrs. Tice regarding communications.
The Mount Holly Reporter also spoke with an engineer at the Green Acres program who stated that Mount Holly Township could proceed in an emergency mode to do the work and recieve approval from Green Acres after the fact. The key being that the township keep the state in the loop regarding its actions.
The Mount Holly Reporter spoke with an engineer at the Burlington County Engineer’s office and it was stated that the timeframe being discussed above is not an unual amount of time for a project of this sort.
A Google search produced a response which indicates that the NJ Department of Transporation [NJDOT] has a 2-year deadline for use of the grant funds provided to Mount Holly after which the funds could be clawed back if the town does not seek an extension.
The Mount Holly Reporter submitted an Open Public Records Act request to the NJDOT for documents regarding the grant and Mount Holly’s correspondence about its progress regarding construction. If this request receives response that is helpful to understanding this story, The Reporter will update its readers.